Foxconn Opticool
Installed for Opticool Technologies a 100 ton chiller and all Piping serving a Pumped refrigerant system that served 18 rolling oracle server racks at the Foxconn manufacturing facility.
TimberTop Condominiums
A Reymsa closed loop cooling tower replaced a 25-year-old Baltimore Aircoil closed loop cooling tower after the old one hemorrhaged the internal tube bundle during the freeze of March, 2021. The new tower, which utilizes an external plate fin heat exchanger serves...
HEB Distribution
Together with the assistance of TNT Crane and Rigging We skated a 150-ton air cooled Quantech chiller and extended all of the piping to accommodate more parking space for the renovation work they are performing on the Genard Building. We also reinisulated the piping...
7676 Woodway
Over the course of a long (Labor Day) weekend, K&R Mechanical Services utilized an 800-ton crane reaching 350 feet to remove two, 20-year-old, Trane RTAA screw chillers. Replaced with two new Carrier, 30XA screw water chillers, we were also contracted to remove all...
The Bunker
The Bunker, a class 1 underground Data Center utilizing multiple stages of redundant chillers in order to maintain the cooling for the servers in place. We were contracted to pipe in 2 owner provided chillers, replace the seals and bearings in the Pumps insulate all...